This guide provides guidance for the planning of preoperational
test programs for Class IE Power Systems for nuclear power
generating stations. The extent of the systems shall be that
covered by ANSI/IEEE Std 308-1980, IEEE Standard Criteria for Class
IE Power Systems for Nuclear Power Generating Stations. An example
system is illustrated in ANSI/IEEE Std 308-1980 [2],1
Fig 1. The power systems are considered to include the ac and dc
power supplies, but do not include the equipment which utilizes the
ac and dc power.
Purpose
The purpose of this guide is to provide direction for
establishing an acceptable preoperational testing program for Class
IE Power Systems in nuclear power generating stations. The
preoperational tests are performed after the appropriate
construction tests have been com· pleted. The purpose of
preoperational tests is to verify that the Class IE Power Systems
perform their required function as designed.
1Numbers in brackets correspond to those of the
refer· ences, Section 3 of this standard.